TIB 2024 ADA Improvements & Overlay

Project Type:
Capital Project
Project Status: 
Approved
Date Received: 
Tuesday, July 2, 2024

Construction is scheduled to begin July 15 with completion at the end of August.

This project provides for three schedules of work.

  • Schedule A includes replacement of seventeen curb ramps on NE 24th Street from Evergreen Point Road to 82nd Avenue NE. 
  • Schedule B includes replacement of seven curb ramps on NE 10th Street at 86th Avenue NE and 87th Avenue NE and also on the west side of Lake Washington Boulevard near NE 10th Street. 
  • Schedule C includes replacement of two curb ramps on NE 10th Street at 88th Avenue NE and the planing and overlay of 88th Avenue NE (south of NE 10th Street) and NE 26th Street (east of 82nd Avenue NE). 

Improvements include, but are not specifically limited to, excavation, cement concrete curb and gutter, cement concrete sidewalk and curb ramps, pavement planing, asphalt paving, pavement markings, pedestrian push button modification, traffic control, and other related work items.

This project meets and supports Council’s priorities 1-5:

  1. Financial Stability and Accountability
  2. Quality Infrastructure
  3. Efficient and Effective Government
  4. Public Safety and Health
  5. Neighborhood Character

Thank you for your patience during this capital improvement project.

 

Project Contact:
Ryan Osada
Public Works Director
City of Medina
425.233.6439
206.423.3278 mobile
rosada@medina-wa.gov