77th Ave NE Stormwater Repair - Phase 1
77th Avenue NE Storm Repair – Phase 1
Scope of Work: This project consists of the construction of approximately 390 feet of storm drainage collection and conveyance improvements on 77th Avenue NE and near 1034 Evergreen Point Road. Work includes, but is not limited to, the removal of 400 linear feet of existing storm drainpipe and associated catch basins, sawcutting and removal of asphalt concrete pavement, removal and replacement of 155 linear feet of concrete curb and gutter, excavation, and the installation of 8-inch, 12-inch, and 15-inch storm drainpipe and associated catch basins, miscellaneous surface restoration, traffic control, erosion control, utility conflict resolution, and other work all in accordance with the attached Contract Plans, these Special Provisions, and the Standard Specifications.
Delivery of Proposal: Mr. Ryan Osada, Public Works Director at rosada@medina-wa.gov
Bid Date: Friday, October 29, 2021 at 2:00 p.m.
Bid Documents may be examined at the office of the City, or the office of the Project Engineer, Gray & Osborne, Inc. Bid Documents for this project are available free-of- charge at the following website: “http://gobids.grayandosborne.com”. Bidders are encouraged to “Register” in order to receive automatic email notification of future addenda and to be placed on the “Bidders List”. For assistance, please call (206) 284-0860. Contract questions shall be directed only to the office of the Project Engineer.
Bidders must be registered on the City’s MRSC Small Works Roster to be eligible to submit a bid for this Project.
Questions concerning the Contract Provisions will be taken by the Project Engineer at Gray & Osborne, Inc.’s Arlington office (360) 454-5490.
No oral responses to questions by City personnel about the project will be binding on the City.
The City expressly reserves the right to reject any or all bids and to waive minor irregularities or informalities, and to further make award of the project to the lowest responsive, responsible bidder as it best serves the interest of the City based on the sum of the Bid.
Status Updates
Jan. 4, 2022:
Due to recent inclement weather, the completion date has been moved to 1/21 22.
Jan. 19, 2022:
Due to asphalt plants being closed for another week and concrete being shutdown due to a labor strike, we now anticipate a new completion date of February 4, 2022.
Jan. 28, 2022
Scope of work expansion will push the anticipated completion date out until the middle of February, 2022.